Parks+Rec

Fort Walton Beach City Council OKs scaled-back Phase 4 scope for The Landing

Fort Walton Beach City Council voted 6-0 Tuesday to advance a reduced Phase 4 scope for The Landing, directing staff to seek architectural services bids.

Source: City of Fort Walton Beach

The Fort Walton Beach City Council voted 6-0 Tuesday, Nov. 17, to move forward with a scaled-back final phase of The Landing Park renovation, directing staff to put together a scope of work and seek bids for architectural services.

The reduced Phase 4 removes the splash pad and the two new restrooms that had been planned for the far ends of the downtown park. Instead, the city plans to give the existing restroom a substantial makeover. City Manager Jason Davis told council he wants to “take that existing restroom and make it the single nicest restroom in the state.”

According to a memo from Davis, splash pads are maintenance intensive, require chemicals and treatments that add to the daily cost of park maintenance, and the park already has a pocket beach and playground for children.

Davis said the decision on the additional restrooms came down to staffing.

“Not that we don’t want them on the distal ends, I just don’t want to add more stuff to take care of, because we’re not adding new staff anytime soon,” Davis said.

The Phase 4 scope would be limited to:

  • Moving the dumpster away from Indianola on the Water.
  • Adding food truck parking and infrastructure to keep trucks off the lawn.
  • Fixing concrete that was not part of the Phase 3 scope.
  • Fixing the playground fencing.
  • Adding bollards to keep vehicles from driving down to the water.
  • Replacing trash cans that were not part of the Phase 3 scope.
  • Adding necessary infrastructure and electric.
  • Replacing missing caps and boards on the pocket beach dock.

The cost will be determined once the scope is finalized, according to the memo, which said the work can be paid for with Community Redevelopment Agency funds.

Davis said the trash cans in particular are falling apart and that the sidewalk concrete that needs repair was outside the Phase 3 contract.

Golf cart parking

Davis also asked council for input on golf cart parking. He said he attended eight or nine of the park’s 10 concerts and saw little golf cart parking in use, but at the last one he attended, every golf cart space was taken.

“It’s too much until it’s not enough, right?” Davis said.

He said the complaints he hears come from drivers who find the vehicle parking full while golf cart spaces sit empty, and who can be ticketed for parking a car in one of those spaces.

“The other part of that argument is the golf carts can park in a regular spot, but a car cannot park in a golf cart spot,” Davis said. “So I kind of think we have too many, but at the same time, we didn’t have enough that one night.”

Police Chief Robert Bage estimated there are close to 30 golf cart spaces, about 20 on one side and 10 on the other. Davis floated adding a loading area so people stop driving down to the seawall, installing bollards, removing some golf cart spaces and, at a minimum, lining up the parking stops with the golf cart spaces.

Council members said they did not want the golf cart question to hold up the project.

  • “I’m not too interested in splitting hairs and figuring out if we do 40 golf cart parking spots or 20,” Councilman David Schmidt said. “I ultimately want to get this kind of product to the next step so that we can bid it out and ultimately come back with the funding for the final phase and call it a day at The Landing.”

Councilman Bryce Jeter agreed, saying he has been at the park on nights when it needed more golf cart parking and nights when it needed more car parking.

“Let’s just get Phase 4 to a scope of work, bid it out, and get it done,” Jeter said.

Restroom capacity

Mayor Nic Allegretto raised a concern about dropping the new restrooms, noting they were a major part of the project when it was first proposed.

“We have these big events and we’re talking about we don’t have enough parking. Do we have enough bathroom space without adding a bathroom?” Allegretto asked.

Davis said he checks the restrooms each time he visits the park to see whether they have been tagged with graffiti.

“I’ve never seen a problem with lines at the bathroom,” Davis said, adding that the city supplements the restrooms with portable toilets during events.

  • City staff told council the men’s restroom has two urinals and one stall, and the women’s restroom has three stalls and a handicap stall.

During public comment, City Council-elect Jeff Pendleton asked about the restrooms’ capacity during full use. He said best practice is one stall for every 50 people over eight hours of use and asked that the city not take away restroom capacity that is needed.

Dave Hancock, who lives at Indianola on the Water, thanked Davis and council for listening to residents’ complaints. He said the parking fills up because the park has become so popular.

“People come down, you see more people and more families down there, which is great,” Hancock said. “That’s what it’s there for. So press on.”

Timeline

Public Works Director Daniel Payne recommended the city bring in a new design team for Phase 4 rather than continue adding work to the existing contract, saying it might take a little more time on the front end.

Davis said the next contract will carry tougher penalties for delays.

“Contract will have much more aggressive liquidated damages this go around, so I don’t expect the delays like I had last time,” Davis said.

Payne said that if council makes the project a priority, it would likely take about five months to complete the bid process, award a contract and be ready to begin work. He noted that a bid package alone takes a minimum of 30 to 45 days. Payne also said a design contract under $100,000 would fall within the city manager’s purchasing authority unless council wanted to review it.

Davis said staff could put the architectural services scope out to bid within about two weeks, depending on purchasing. He added that he does not want construction to begin until after next year’s concert series, with the work finished before October.

Schmidt made the motion, which was seconded by Councilman Browning. Councilman Payne Walker was absent. Staff is expected to update council at its next meeting on Dec. 15. Davis said he would let council know if the item is not ready by then.

Background

In August, council voted 6-0 to close out Phase 4 with a scaled-down scope rather than the full buildout. Phases 2 and 3 of The Landing were completed this year, and the park reopened with a ribbon cutting April 24. The project has cost roughly $8 million through Phase 3, funded through sources including NRDA grants, RESTORE Act dollars, Tourist Development Council revenue, the half-cent infrastructure surtax and CRA funds.

Eglin Federal Credit Union recently signed a three-year naming rights deal for The Landing.

Free newsletter

Never miss a local story

Join thousands of locals who get the day's Okaloosa and Walton news from Get The Coast, free every weekday morning.
Free. Unsubscribe anytime.

Rather not get email? You can still help keep local news free. Support local news

Thanks for reading

Help keep local news free

Get The Coast is free to read, every day. Support from readers like you keeps it that way.
Support local news
Prefer Get The Coast on Google See our stories first when you search local news. Add as preferred source
Comment

Join the conversation...

More stories

Community Comments

“My family and I very much appreciate everyone’s participation in honoring Dad. It is heart-warming to observe the reverence and respect shown to a special man who has devoted his...”
Respond
“My family and I very much appreciate everyone’s participation in honoring Dad.  It is heart-warming to observe the reverence and respect shown to a special man who has devoted his...”
Respond
“Hopefully I am at Harbor Docks”
Respond
“Re storm removal....no mention of Shalimar or Poquito Bayou! The piles are just getting higher!!”
Respond
“where can I find more information for applying and qualification please. Rossie.wade@gmail .com”
Respond
Sue Schaeffler commented on WordroW: November 17, 2026
“0:43, 4 attempts”
Respond
“Thanks Jared for always keeping us informed.”
Respond
“The plan shows the existing 4 lane section of SR85 between 12th Ave. and the entrance to Shalimar Elementary remaining yet both ends of this section are to be 6...”
Respond
“Why would the upper decks not be accessible to divers. The one photograph I have seen may show a slight list to port, but it is not clear if that...”
Respond