New westbound Brooks Bridge structure opens to Highway 98 traffic in Fort Walton Beach
Westbound U.S. 98 drivers are now using the new Brooks Bridge structure, while eastbound traffic stays on the existing 1966 bridge for several more weeks.
U.S. Highway 98 westbound traffic is now traveling on the newly constructed westbound structure of the Brooks Bridge between the Destin-Fort Walton Beach Convention Center on Okaloosa Island and Perry Avenue in Fort Walton Beach.
The opening is part of the project’s phased opening plan, according to a project update. U.S. 98 eastbound traffic will remain on the existing Brooks Bridge, and all four U.S. 98 travel lanes, two in each direction, will stay open throughout construction.
Several changes to traffic patterns around Santa Rosa Boulevard are now in place:
- Westbound U.S. 98 motorists will reach Santa Rosa Boulevard by using a new connector roadway west of the convention center, then proceeding to the roundabout.
- Northbound Santa Rosa Boulevard motorists heading to westbound U.S. 98 will go through the U.S. 98 signalized intersection, continue to the roundabout, and use the new connector road and access ramp to enter the westbound structure.
- Eastbound U.S. 98 motorists are not permitted to turn left onto northbound Santa Rosa Boulevard. To reach Santa Rosa Boulevard, drivers will continue east on U.S. 98 and use the designated connector road.

Pedestrians will continue to use the sidewalks on the south side of the existing bridge, next to the eastbound U.S. 98 travel lanes. Signage will be in place to direct traffic through the new pattern.
The current configuration is expected to stay in place for several weeks before another traffic shift moves eastbound U.S. 98 lanes onto the new westbound structure. Once all traffic has been moved to the new structure, crews will demolish the existing bridge and begin building the eastbound portion of the new Brooks Bridge.
Intermittent lane closures may occur on U.S. 98 from Ferry Road to Pier Road between 9 p.m. and 5:30 a.m., Sunday through Thursday.
The $171 million Brooks Bridge Replacement Project includes construction of two new parallel bridges that will increase capacity to six travel lanes, up from the four lanes on the current bridge, which opened in 1966. The project is scheduled for completion in early 2029.
All work is weather dependent and may be delayed or rescheduled in the event of inclement weather. Drivers are reminded to use caution when traveling through the work zone, especially at night, and to watch for construction workers and equipment entering and exiting the roadway.