Search
Close this search box.

Destin’s Norriego Point project update reveals summer completion timeline

The Norriego Point development project continues to advance with multiple construction phases, including shoreline stabilization and boardwalk installation, targeting completion in summer 2025.
Aerial view of Norriego Point shows the boardwalk terminal curve at 60% completion, with shoreline stabilization work nearing 90% completion along the harbor entrance. The site, scheduled for final completion in June 2025, includes locations for three dune crossovers and a future restroom facility. (City of Destin)

Construction at Norriego Point continues with shoreline stabilization, boardwalk pilings, and dune crossovers nearing various stages of completion, according to a Department of Environmental Protection project update shared at Monday’s Destin City Council meeting.

  • Public Information Director Tamara Young reported that shoreline stabilization work at the harbor entrance, including site grading and placement mats, is 90% complete and scheduled for completion this week.

The project’s boardwalk infrastructure is taking shape, with 50% of pilings now installed, including all piles for the terminal curve at the north end. Dune crossover pilings are 80% complete, while all pilings for the restroom and pavilion have been installed.

Young noted that framing on the boardwalk terminal curve has reached 60% completion, and work on the northernmost dune crossover, number 3, is 20% complete.

The next 30 days will see several major components move forward. Construction of the restroom facility will begin, with completion targeted for mid-May. The remaining boardwalk pilings are scheduled for completion by mid-February.

  • Framing and decking work for all three dune crossovers is set to begin, with completion expected by mid-March. The harbor boardwalk framing and decking will follow, scheduled for completion in mid-April.

Staff and council members will review color boards for the interior and exterior of the restroom, as well as pavilion and restroom roofing options, for final approval.

The project is on track for substantial completion in late May, with final completion expected by late June 2025.

PROMOTION

3 Responses

  1. So who actually is paying for this? And isn’t this private property? And if it’s not private property, why isn’t there more accessible parking available for all?

Join the conversation...

Continue reading 👇

Community Comments

“This was a fun game to watch.”
Respond
“This team is absolutely headed in the right direction with current leadership. I love they way they do things and I believe this will be a premier program very soon,...”
Respond
“I love that the golf course is doing well, but I wonder if we are pricing out local players. A 50% increase in cart fees is pretty steep and would...”
Respond
“been issues since know we now they were bought out by a big franchise”
Respond
“I went with Adams because it was local owned and provided great service and good prices. I was wondering why the service has slip the last few months. They may...”
Respond
Scott Schaeffler commented on WordroW: August 26, 2026
“1:51, 5 attempts”
Respond
Scott Schaeffler commented on WordroW: August 25, 2026
“1:38, 5 attempts”
Respond
“What are the symptoms that the person gets from West Nile virus”
Respond
Scott Schaeffler commented on WordroW: August 24, 2026
“1:19, 5 attempts”
Respond
“We also need to be alerted when these advisory are issued. How are we supposed to find out about them? We were in the water over the weekend since the...”
Respond

GET OUR FREE LOCAL NEWSLETTER

Get the weekday email that actually makes reading local news enjoyable again.